Upcoming IPO In Nepal: Nyadi Hydropower To Issue IPO

Nyadi Hydropower, promoted by Butwal Power Company Limited (BPCL) and Lamjung Electricity Development Company Ltd. (LEDCO) is going to issue IPO. Nyadi Hydropower is issuing an IPO of 40.50 lakh units of shares. After the IPO issue, the paid-up capital of the Nyadi Hydropower will be Rs. 1.5 Arba.

Nyadi Hydropower Limited is a public company, incorporated on March 1, 2007.

Upcoming IPO In Nepal: Nyadi Hydropower To Issue IPO

SEBON approved the IPO proposal on Shrawan 11. Global IME Capital has been appointed the issue manager. Citizen Investment Trust is appointed as the underwriter of the Nyadi Hydropower IPO issue.

Nyadi Hydropower Project (NHP) is a run-of-river type project, located in Lamjung District of Western Development Region of Nepal. The hydro project is located within the Bahundanda Village Development Committee (VDC) in Lamjung District, Gandaki Zone on the right bank of Nyadi Khola which is one of the tributaries of the Marsyangdi River. The project has an installed capacity of 30 MW and will generate 168.5 GWh of energy annually.

Facts Of Nyadi Hydropower Project

Technical features of the project
Type of the projectRun-of-the River
Project locationBahundanda VDC, Lamjung District
Dam siteNaiche, Bahundanda VDC, Ward 2
Powerhouse siteBahundanda VDC, Ward No.7
Installed Capacity30 MW
Average annual energy168.5 GWh
Gross head333.9 m
Design flow11.02 m3/s
Catchment area at intake site154.7 km2
Design Flood Discharge509 m3/s (100 Yrs Flood)
Settling basin128 m (L), 8 m (W), 10 m (H)
Length of Headrace tunnel3.937 km
Turbine typeHorizontal Axis Pelton
Turbine Installation3 nos. with 10 MW capacity
Transmission Line7 km long of 132 kV capacity
Construction period4 years

 